All Case Studies

Migration

Zero-Downtime Datacenter Exit — 180 Workloads to Azure Landing Zones

An industrial manufacturer migrated 180 production workloads to Azure with phased waves, automated assessments, and near-zero customer impact.

Zero-Downtime Datacenter Exit — 180 Workloads to Azure Landing Zones

Executive Summary

Lease expiry forced a rapid exit from a legacy datacenter. We designed Azure landing zones and executed a risk-based migration factory.

Challenge

Tight cutover windows, interdependent apps, and limited documentation.

Solution

Discovery + dependency mapping, landing-zone foundations, pilot waves, and automated cutover runbooks.

Outcomes

On-time exit, improved resilience, and a reusable migration playbook for remaining estates.

  • 180 workloads migrated
  • Near-zero customer impact
  • Reusable factory playbook